Heat Pump Installation.
Commencing Monday 16th September 2024.
Wednesday 18th September.
Page 1
Page 2
Page 3
Page 4
External pipework started and hot cylinder pipework continues Wednesday 18th September.
Conduit and lagged pipe detail.
A pallet of cable sent back...
Electrician due on Thursday 19th September.
Thursday 19th September.
Filling work and outlet cage.
Limestone chip soakaway area.
Electrician on site.
Old expansion pipes removed.
Heat pump piping and power cable route.
Power cable route and capped gas pipe.
Power cable installation.
External power switch.
Power and control cable terminations.
New Fuse Box supply connected.
Power supply tested and unit secured ready for commissioning on Friday 20th September.
Friday 20th September.
Control Panels.
Fuseboards.
External temperature sensor.
Up and running c12:15 Friday 20th September.
Final lagging.
Meter reading 24 hours after start-up, c11:45 21st September 2024.
The residue of materials. The radiators and miscellaneous supplies were removed on 30th October leaving the buffer tank in residence.